Photo of Kimberly R. Nason

Under New York State Public Service Law Section 66-j, certain remote net metered renewable energy projects, including solar energy facilities, are limited to 2 MW on a single deeded parcel in order to qualify for net metering.

The Public Service Commission (“PSC”), in its December 14, 2014 “Order Raising Net Metering Minimum Caps, Requiring Tariff Revisions, Making Other Findings, and Establishing Further Procedures” (“December Order”), addressed the 2 MW issue. In clarifying the 2 MW limitation, the PSC addressed requests from Cornell University regarding whether, under the limitation, a non-residential solar customer can collocate multiple 2 MW remote net metered projects on adjacent or contiguous parcels. Continue Reading New York State Public Service Commission Order on Remote Net Metering May Require Solar Projects to Obtain Subdivision or Lot Line Adjustment Approvals